picture of Construction Progress Update – Week 39 | Rothesay House

Construction Progress Update – Week 39 | Rothesay House

Construction Progress Update – Week 39 | Rothesay House

March 11, 2025
2-3 mins read

As of Week 39 of construction at Rothesay House, the development is progressing at a rapid pace. This student accommodation in Bournemouth is on track, with roof construction set to begin this week as we approach a significant milestone: making the building weather tight.

External Progress of Student Accommodation in Bournemouth

 

Close-up front view of the student accommodation building with six floors already built.

  • The metal frame is nearing completion, with work on the 7th floor scheduled for this week. Once finished, roof construction will commence using roofing cassettes for streamlined logistics.
  • Scaffolding is now almost complete, and masonry work has progressed to the 4th floor.
  • The main reception and front entrance feature stonework are now fully completed.

Internal Progress

 

Site manager overseeing construction inside the building, surrounded by Metsec panels.

  • Temporary weatherproofing has been installed on four floors, allowing internal work to continue while the permanent roof is being finalised.
  • Most of the bathroom pods have now been installed, significantly accelerating the internal fit-out process.
  • Mechanical and electrical installations have advanced from the ground floor up to the third floor.
  • Lightweight metal walls have made steady progress throughout the building.
  • Fire safety and general production are advancing efficiently.

What’s Next?

 

Close-up aerial view of a student accommodation construction site, with the floor structure clearly taking shape.

In the coming weeks, our focus will be on:

  • Further masonry work
  • Final bathroom pod installations
  • Roof construction
  • Internal works, including partitioning and plastering
  • Progress on fire safety, mechanical, and electrical systems
  • Refinement of the building’s external facade

Final Thoughts

 

View from Rothesay House construction site towards the sea, featuring the Bournemouth Big Wheel.

Rothesay House is a hive of activity, with significant advancements every week. We’re excited to see the project moving closer to completion and look forward to sharing further updates soon. Stay tuned for more progress!

Foruni: A New Standard For Student Living

 

CGI of the luxury student accommodation building, showing the final exterior design.

Foruni is a purpose-built student accommodation in Bournemouth brand, designed to provide high-quality, modern living spaces in prime locations. Rothesay House, situated on Hinton Road in Bournemouth, is set to open in September 2025, offering a safe, stylish, and community-focused environment for students. For more information on student life in Bournemouth, including local university resources, visit Bournemouth University.